March 1, 2024
Started installation of metal structures of the production block. 8557 m2 of sandwich panels were delivered to the construction site. In March 2024, 190 tons of metal structures were installed. The remaining 310 tons of construction metal structures are in production. Completion of delivery and installation is expected in May 2024